Auckland’s rail community is a significant step nearer to a contemporary, extra dependable metro system with the completion of the ultimate large-scale pre-Metropolis Rail Hyperlink works, say Rail Minister Winston Peters, Transport Minister Chris Bishop, and Auckland Mayor Wayne Brown.
“The previous few weeks of onerous graft symbolize a significant achievement for public transport and freight in Auckland,” Peters says.
“After 5 years of sustained, weeks-long disruptions, rail work will more and more be delivered in brief, focused closures timed for intervals of decrease demand that deliver Auckland into line with how trendy networks are maintained abroad.
“That sustained disruption has strengthened the community forward of the Metropolis Rail Hyperlink to deal with extra frequent trains and builds on main accomplished upgrades equivalent to extending electrification to Pukekohe and delivering a 3rd essential line via the busiest rail junction – work we began in 2020,” Peters says.
“We thank commuters for his or her endurance with bus replacements, and the various staff throughout KiwiRail, Auckland Transport, Metropolis Rail Hyperlink Ltd and subbies [subcontractors] who put within the onerous yards.”
Bishop says the completion of the ultimate large-scale pre-CRL works marks the tip of essentially the most disruptive section of rail upgrades in Auckland.
“With trains now again operating totally following the four-week summer time closure, the five-year programme to rebuild the busiest and most important components of the community is full.
“This work has rebuilt Auckland’s rail community from the foundations up, so it’s able to help Metropolis Rail Hyperlink and ship extra trains, extra usually, with far larger reliability.

“Successive governments have invested greater than $560 million – together with $159m in Funds 2024 – to hold out the work,” Bishop says.
“We’d wish to recognise the efforts of the 1300-plus individuals who labored throughout greater than 300 websites in the course of the 2025-26 summer time rail improve.”
Over the course of Auckland’s summer time rail closure, groups changed foundations and monitor, put in new drainage, renewed key rail elements, eliminated two stage crossings, and carried out the primary full network-wide check of the CRL timetable.
“That check noticed 84 trains working throughout the community on the identical time, the most important quantity ever run concurrently on Auckland’s metro rail system,” Bishop says.
“The toughest and most disruptive work is now behind us. There actually is mild on the finish of the tunnel.
“Whereas there’ll nonetheless be a number of extra line closures previous to Metropolis Rail Hyperlink’s opening, these closures are anticipated to be a lot shorter and fewer disruptive.
“What Aucklanders ought to anticipate from here’s a extra dependable community, fewer lengthy shutdowns, and a rail system able to ship the complete advantages of Metropolis Rail Hyperlink.”
Brown says the milestone reveals tangible progress for Aucklanders after years of disruption.

“It has been a protracted and irritating time for Aucklanders, particularly companies who’ve needed to put up with disruption for years, so I thank them for his or her endurance as this venture has been accomplished.
“It’s essentially the most advanced venture undertaken in New Zealand however there may be payoff coming for Auckland.
“One in every of my key insurance policies is to Get Auckland Transferring and Metropolis Rail Hyperlink will ship a stronger, safer rail community that may help extra frequent providers, cut back congestion and higher join the town because it continues to develop.”
The summer time works additionally delivered key enhancements at main stations. On the Western Line, progress at Henderson Station means each tracks are actually working, restoring peak-time providers to their normal 10-minute frequency.
Main progress has additionally been made at Takanini, Glen Innes, and Te Mahia (Manurewa/Takanini) with piling largely full and carry shafts now properly beneath manner for brand spanking new pedestrian bridges that can completely substitute stage crossings later this 12 months.
Metropolis Rail Hyperlink Ltd, Auckland Transport and KiwiRail are actually targeted on additional testing and commissioning forward of opening.
Extra quick closures are deliberate within the lead-up to CRL opening, with disruption largely restricted to weekends and public holidays wherever potential.
Auckland summer time rail works programme – key info and figures
Some 1300-plus folks labored throughout the Auckland metro community.
5-year rail community rebuild (RNR) is now full forward of CRL opening.
Eighty-four trains had been used within the first full network-wide check of the longer term CRL timetable.
For the reason that RNR started greater than 80 kilometres of monitor throughout the 182km Auckland community has been changed.
Some 1600-plus sleepers had been changed and 20 crossover turnouts put in.
Six kilometres of drainage and 6km of foundations changed.
Two extra stage crossings eliminated and main station upgrades delivered.