The much-anticipated Reeves Highway Flyover – Rā Hihi – partially opens subsequent week and as ceremonies are held for it in the present day Friday, attended by elected representatives from native and central governments, PJ TAYLOR plots its course to completion.
East Aucklanders have known as for street transport options for a few years now, because the space’s inhabitants began rising rapidly and considerably within the Nineties.
Because the numbers of individuals dwelling within the east has grown, so has the quantity of motor autos they drive.
Highway routes attending to and from different elements of Auckland have turn out to be frustratingly extra congested, as many can attest to by way of their very own experiences of gridlock.
It’s not a novel expertise for east Aucklanders, as others throughout the Auckland area have additionally endured and proceed to crawl by way of annoying over-congestion of their areas day by day.

Common gridlock is a symptom of ongoing rising pains of a preferred metropolis that retains attracting individuals.
There’s no finish in sight and the record of main infrastructure jobs Auckland requires retains getting larger, too.
The arrival of the Howick ward’s largest public infrastructure asset in many years – Rā Hihi, the Reeves Highway Flyover – is blessed and celebrated in the present day, September 26, to partially open subsequent Wednesday, October 1.
Two lanes on the Rā Hihi overpass will then be open to autos travelling away from the east.
It’s as a consequence of absolutely open with its 4 lanes operational from Labour Day, October 27.

Publicly elected members in the present day shall be jovial and congratulating concerning the flyover’s supply, delighted the challenge has are available in below funds and sooner than first anticipated.
Beforehand, it was as a consequence of open early subsequent 12 months, after development commenced 18 months in the past.
Auckland Transport (AT), builders of the flyover with the Jap Busway Alliance, has instructed the Instances the challenge has value $152 million, coming in “greater than $4m below funds”.
AT’s additionally been fixed on document saying: “It’s [the flyover] an vital a part of the Jap Busway challenge that can enhance journey occasions and ease congestion within the space.
“Establishing this direct hyperlink between Pakūranga Highway and the South-Jap Freeway will result in a discount in site visitors alongside Pakūranga Highway and Tī Rākau Drive, significantly throughout peak hours.

“Work to construct Rā Hihi started in March 2024 and it’ll take roughly two years to finish,” stated AT.
“Throughout that point, entry to the Pakūranga city centre, native companies and houses are being maintained to minimise disruption to the group.”
Regardless of AT’s messaging, development work on the flyover challenge has undoubtedly had a extreme damaging affect on the financial fortunes of Pakūranga Plaza and the native companies buying and selling within the Pakūranga city centre precinct, because the Instances has reported in a collection of stories tales over the previous 12 months. (Story hyperlinks beneath).
The main development works have gone straight by way of the center of the city centre precinct and over it, inflicting severe disruptions to enterprise and group actions there, together with entry.
One can solely hope, for the sake of the prosperity of people that have companies at Pakūranga Plaza and within the adjoining space, that AT’s assertion will eventuate: “Boosting the financial vitality and sustainability of east Auckland by way of improved transport connections.”

Though AT’s positively upbeat about lowering congestion, as many east Aucklanders have identified in suggestions to the Instances over a protracted interval, nobody actually is aware of whether or not the flyover will do this, or simply turn out to be one other congested street particularly throughout peaks.
Time will inform, however it’s going to little doubt be faster to get from Pakūranga Highway to the South-Jap Freeway in different lesser busy intervals.
Rā Hihi interprets to solar’s rays, or ray of solar, a reputation description gifted by native iwi, Ngai Tai ki Tamaki.
AT says the unmissable large construction is “embracing parts of te ao Māori and sustainable design such because the revolutionary reuse of stormwater runoff and weaving cultural richness into the infrastructure with bespoke mahi toi / art work”.

Rā Hihi, by numbers
It’s 600 metres lengthy, 18m large, and 10m excessive.
There are 17 sections (spans), supported by 16 piers.
The longest span reaches 40m over Tī Rākau Drive.
There are 136 Tremendous T beams, with eight in every part/span.
The heaviest beam weighs 90 tonnes.
There are 4 lanes for site visitors, two for every path.
Every pile is 30m deep.
It’s product of 11,500 cubic metres of concrete, and 2500 tonnes of reinforcing and pre-stressing metal.
There are 24 basis piles, 16 which might be 3m throughout, and eight 1.5m throughout.

For current Instances’ tales and pictures concerning the Rā Hihi flyover, learn:
https://www.occasions.co.nz/enterprise/saluting-flyover-heroes-early-opening-for-new-roadway/
https://www.occasions.co.nz/local-business/new-photos-released-of-flyovers-progress/
https://www.occasions.co.nz/information/motorists-warned-to-expect-more-delays-in-pakuranga/
https://www.occasions.co.nz/enterprise/exclusive-photos-plot-progress-of-ra-hihi-reeves-road-flyover/







For earlier Instances’ tales about Pakūranga Plaza and the city centre, learn:
https://www.occasions.co.nz/enterprise/pakuranga-plaza-the-good-the-bad-and-no-news/
https://www.occasions.co.nz/enterprise/exclusive-the-warehouse-at-pakuranga-plaza-is-closing/
https://www.occasions.co.nz/information/christmas-present-for-pakuranga-plaza-and-woolworths-says-sorry-to-customers/
https://www.occasions.co.nz/information/theres-a-kind-of-hush-at-a-pakuranga-plaza-christmas/
https://www.occasions.co.nz/information/pain-down-at-pakuranga-plaza/
https://www.occasions.co.nz/information/auckland-transport-responds-to-concerns-at-the-plaza/
https://www.occasions.co.nz/enterprise/cheerleader-collings-flies-flag-for-pakuranga-plaza/
https://www.occasions.co.nz/information/busway-construction-drives-pharmacy-from-pakuranga-plaza/
https://www.occasions.co.nz/enterprise/mp-weighs-into-debate-over-problems-at-plaza/
https://www.occasions.co.nz/enterprise/public-opinion-on-the-pain-at-the-plaza/





:max_bytes(150000):strip_icc()/Health-GettyImages-HealthBenefitsOfPecans-105fb031cbe64298b811e3ae701f2ce8.jpg)